                         (A) 
                          Scope 
                          The 
                          manhole base liner shall be a FIBERGLASS REINFORCED 
                          PLASTIC (F.R.P.) BASE LINER SYSTEM, which is resistant 
                          to the chemical environment normally found in wastewater 
                          transmission systems. The F.R.P. Base Liner shall be 
                          a non-load bearing component integrally cast and adequately 
                          anchored inside new precast concrete manhole base sections 
                          during concrete casting process at the concrete precaster's 
                          manufacturing facility 
                       | 
                       
                         (B) 
                          FIBERGLASS MANHOLE BASE LINER 
                          (1) The prefabricated F.R.P. base liner shall be a one 
                          piece construction of unlayered, homogenous composite 
                          with minimum thickness shall be 1/8" (3 mm) and shall 
                          be in lengths and nominal inside diameters corresponding 
                          to the precast concrete base section. 
                          (2) The prefabricated F.R.P. manhole base liner shall 
                          include full flow channels with side walls to the crown 
                          of the pipe; inner surface of the bench to have an anti-skid 
                          pattern; watertight gasketed pipe bell connections or 
                          F.R.P. / PVC boot hole sleeves to suit specific pipe 
                          types, grade and alignment, shall be monolithically 
                          attached to prefabricated F.R.P. base liners to extend 
                          to the outside profile of the precast concrete structure 
                          per drawing details. 
                          (3) The outer surface of the liner to be aggregate coated 
                          and have steel spirals/ lattice bonded to the F.R.P. 
                          to insure adequate anchoring to concrete base sections 
                          to pass vacuum test with 10" of negative pressure.  
                       | 
                    
                     
                      |  
                         (C) 
                          INSTALLATION IN PRECAST CONCRETE 
                          (1) 
                          The F.R.P. base liner shall be cast integral with the 
                          precast concrete manhole base section in accordance 
                          with the liner manufacturer's specifications. The liner 
                          must be fully supported during the casting process; 
                          lifting devices shall not penetrate inside walls F.R.P. 
                          base liner. 
                          (2) Inside F.R.P. liner surfaces shall be free of bulges, 
                          dents and other defects that result in a variation of 
                          inside diameter of more than 1/4" (7 mm) for base liner 
                          flow channel and pipe connections. The precast concrete 
                          pipe penetration joint surfaces shall be free of excess 
                          concrete at external and internal surfaces to insure 
                          proper seal of pipe connection and F.R.P. liner. 
                       | 
                       
                         (D) 
                          FIELD ASSEMBLY AND INSPECTION PRECAST CONCRETE MANHOLE 
                          WITH F.R.P. LINER 
                          (1) 
                          During the field installation of F.R.P. lined precast 
                          manhole base sections; all pipe connections are to be 
                          sealed per the liner manufacturer's standard method 
                          and details. Precast concrete sections shall be sealed 
                          as prescribed by precast manufacturer and utility specifications. 
                          (2) The interior surfaces of the liner shall be completely 
                          free from pinholes, cracks, pits or defects that are 
                          detrimental to the intended use of the F.R.P. base liner. 
                          No F.R.P. base liner shall have holes, or openings, 
                          which will permit the passage of liquid or gases through 
                          the liner wall to precast concrete. There shall be no 
                          exposed concrete mortar through inside liner surface 
                          to include (but not limited to) pipe penetrations. All 
                          mechanical anchor attachments through liner surfaces 
                          must be sealed with an approved elastomeric sealant. 
                          Consult liner manufacturer for specific information 
                          regarding approved sealant supplier list and availability. 
                       |